Time: 2023-07-21 15:55:42
Author: Hebei Allland steel pipe manufacturing Co., Ltd.
Click:
1. Plate testing: after the steel plate used to manufacture large diameter submerged arc welding straight seam steel pipe enters the production line, the first full plate ultrasonic inspection is conducted;
2. Edge milling: Double sided milling is performed on the two edges of the steel plate using an edge milling machine to achieve the required plate width, edge parallelism, and groove shape;
3. Pre bending edge: Use a pre bending machine to pre bends the edge of the plate, so that the edge has the required curvature;
4. Forming: On the JCO molding machine, first half of the pre bent steel plate is stamped multiple times to form a "J" shape, and then the other half of the steel plate is also bent to form a "C" shape, forming an open "O" shape
5. Pre welding: Make the formed straight seam welded steel pipe joint and use gas shielded welding (MAG) for continuous welding;
6. Internal welding: longitudinal multi wire submerged arc welding (mostly four wire) is used to weld on the inner side of straight seam steel pipe;
7. External welding: longitudinal multi wire submerged arc welding is used to weld outside the longitudinal submerged arc welding steel pipe;
8. Ultrasonic Inspection I: Inspection of the inner and outer welds of straight welded steel pipes and the base metal on both sides of the welds;
9. X-ray inspection I: X-ray industrial television inspection of internal and external welds, using an image processing system to improve the sensitivity of the inspection;
10. Expanding: expand the whole length of submerged arc welding straight seam steel pipe to improve the dimensional accuracy of steel pipe and improve the distribution of stress in steel pipe;
11. Hydrostatic test: The expanded steel pipes are inspected one by one on a hydraulic testing machine to meet the required test pressure. The machine has automatic recording and storage functions;
12. Chamfering: Process the qualified steel pipe at the pipe end to meet the required pipe end groove size;
13. Ultrasonic inspection II: Conduct ultrasonic inspection one by one again to check the possible occurrence of longitudinal welded steel pipes after expansion and water pressure;
14. X-ray inspection II: Conduct X-ray industrial television inspection and take photos of pipe end welds on steel pipes after expansion and hydraulic testing;
15. Magnetic particle inspection of the pipe end: Conduct this inspection to discover the pipe end;
16. Corrosion prevention and coating: Qualified steel pipes shall undergo corrosion prevention and coating according to user requirements.